How long does it take to replace the roof on a small commercial building?

Owners of small commercial buildings ask the same thing homeowners do, plus one more question: what happens to the business while the roof is being replaced? Here is how a two-day roof replacement on a retail store in Wayzata went in October.
Day one: tear-off, decking and underlayment
The old shingles came off and the roof deck was checked. Then synthetic underlayment went down over the whole roof, and the shingle bundles were staged on the roof for the next morning.




Day two: shingles, ridge and cleanup
The new shingles went on, then the ridge, and the site was cleaned up.


What makes a roof replacement take longer
- Size and roof type. Large low-slope roofs are often done in sections over several days or weeks.
- Weather. The roof is only opened up when the forecast allows it to be closed the same day.
- Decking repairs. Rotted or soft decking found during the tear-off has to be replaced first.
- Materials. Special-order shingles, metal or membrane can set the start date.
Keeping the business open
Talk with the contractor before the job about entrances, parking and deliveries, where the dumpster and materials will sit, and how cleanup is handled each day. Tear-off is the noisy part, and it is usually the first morning.
Planning a roof for a shop, office or rental property? Request a free estimate or see our commercial roofing services.
Frequently asked questions
How long does a commercial roof replacement take?
It depends on size, roof type and weather. A small single-story building with a shingle roof can take one to three days of roof work; large flat roofs take longer and are often done in sections.
Can a business stay open during a roof replacement?
Often, yes. Plan entrances, parking, deliveries and daily cleanup with the contractor ahead of time, and expect noise during the tear-off.
What goes under new shingles on a commercial building?
The decking is checked and repaired, then underlayment, ice and water protection where it is needed, drip edge and flashing go down before the shingles.
How long did the roof replacement on the Wayzata retail store take?
Two days in October. Day one: tear-off, a check of the roof deck and synthetic underlayment, with the shingles staged on the roof. Day two: new shingles, the ridge and cleanup.